A step-free footbridge at Oxhey Grange will be lifted into place in December and open in late January. See the plans in South Oxhey on 16 November.

A new footbridge over the railway at Oxhey Grange is due to open in late January, restoring the path between Anthony Close and the playing fields on the Watford side. Network Rail has ordered the structure from a bridge supplier and expects to lift it into place in December, then test it before it opens. Residents can see the plans at a drop-in between 4.30pm and 6.30pm on Monday 16 November at Colnbrook School in Hayling Road, South Oxhey, where Network Rail staff will answer questions.

The old footbridge was closed after significant, urgent defects were found in its structure in July, and Network Rail lifted it out after emergency works in September, leaving the public right of way across six railway lines cut ever since. Our travel page has followed the closure.

What the new bridge will be like

Network Rail calls the replacement an “interim” bridge, but says it has a long lifespan. It still intends to put up a permanent structure when funding is available.

The bridge will be 2.35m wide with sides 1.8m high, painted a colour described as holly green. It will have no steps: a gentle ramp at each end leads up to an even deck with an anti-slip surface.

The plans were set out at an online briefing by Network Rail’s Principal Route Engineer, Lei Wang, and Mark Evans, a contractor engineer working for Network Rail. Watford’s MP, Matt Turmaine, was among those who joined it.

“I am glad that plans are well underway to restore the connection above the six railway lines which will reopen the public footpath and right of way between Anthony Close and the playing fields on the Watford side,” Mr Turmaine said.

“It will be step-free which is important, will have a gentle access ramp at either end and an even surface with anti-slip texture,” he said.

Dates so far

  • December: the bridge is lifted into place, then tested.
  • Late January: due to open to the public.
  • Monday 16 November, 4.30pm to 6.30pm: plans on show at Colnbrook School, Hayling Road, South Oxhey.